Welcome to the article Newhard Company assigns overhead cost to jobs on the basis of 114 of direct labor cost The job cost sheet for Job 313 includes 26. On this page, you will learn the essential and logical steps to better understand the topic being discussed. We hope the information provided helps you gain valuable insights and is easy to follow. Let’s begin the discussion!

Newhard Company assigns overhead cost to jobs on the basis of 114% of direct labor cost. The job cost sheet for Job 313 includes $26,530 in direct materials cost and $10,500 in direct labor cost. A total of 1,400 units were produced in Job 313.

Required:
a. What is the total manufacturing cost assigned to Job 313?
b. What is the unit product cost for Job 313?

Answer :

Answer:

Results are below.

Explanation:

Giving the following information:

Estimated overhead rate= 114% of direct labor cost.

Job 313:

Direct materials= $26,530

Direct labor= 10,500

Number of units= 1,400

First, we need to allocate overhead to Job 313:

Allocated MOH= Estimated manufacturing overhead rate* Actual amount of allocation base

Allocated MOH= 10,500*1.14= $11,970

Now, the total cost:

Total cost= 26,530 + 10,500 + 11,970

Total cost= $49,000

Finally, the unitary cost:

Unitary cost= 49,000 / 1,400

Unitary cost= $35

Thank you for reading the article Newhard Company assigns overhead cost to jobs on the basis of 114 of direct labor cost The job cost sheet for Job 313 includes 26. We hope the information provided is useful and helps you understand this topic better. Feel free to explore more helpful content on our website!